Campus network

Current initiative Phased, Sept 2026 to Aug 2029

Wi-Fi Optimization

A campus-wide initiative to strengthen wireless coverage and create a more consistent experience for teaching, research, and operations, building a strong, sustainable wireless foundation for the future.

What is Wi-Fi Optimization?

A stronger wireless foundation for campus

A campus-wide initiative to strengthen wireless coverage and create a more consistent experience for teaching, research, and operations, building a strong, sustainable wireless foundation for the future.

Why it matters

Reliable wireless reduces disruptions to teaching and research, enables a “Wi-Fi first” approach, and supports long-term cost avoidance across campus.

Initiative objectives

Four core objectives

A systematic, campus-wide effort organized around four objectives.

1

Survey coverage

Conduct Wi-Fi coverage surveys across campus buildings to identify coverage deficiencies.

2

Design

Create wireless designs that support optimal coverage and capacity.

3

Implement

Implement recommended designs in all E&G (Education and General) spaces.

4

Plan ahead

Develop recommended designs for auxiliary spaces for future funding consideration.

Key benefits

What changes for campus

Improved reliability

Improved wireless reliability, reducing disruptions to teaching, research, and daily operations.

“Wi-Fi first” approach

Enablement of a “Wi-Fi first” network approach, supporting long-term cost avoidance.

A modern foundation

A modern wireless foundation to support future technologies and evolving security needs.

A multiyear, phased effort

Three phases, highest impact first

The initiative is phased to address the highest-impact spaces first. Scheduling factors in current Wi-Fi coverage, impact to teaching and research, and accessibility of space in light of construction and operational activities.

Phase 1

Highest-impact spaces

Approx. Sept 2026 to Aug 2027

75

buildings

Phase 2

Continued rollout

Approx. Sept 2027 to Aug 2028

53

buildings

Phase 3

Campus completion

Approx. Sept 2028 to Aug 2029

101

buildings

Phase dates are approximate, targeted timeframes and may shift as the rollout proceeds.

Building tracker

229 buildings are scheduled across the three phases. Track each building’s survey, installation, and validation status.

What to expect

Three stages for every building

Each building moves through three stages. Activities are scheduled in advance and communicated to building contacts.

Stage 1

Survey and design

Enterprise Technology staff will be on-site conducting scheduled site surveys.

Stage 2

Installation

Installation crews will be on-site installing cables and wireless access points to ceilings. Activities will be scheduled in advance and may involve brief, localized disruption to wireless networking and installation-related noise. Accessibility to areas will not generally be impacted.

Stage 3

Validation

Enterprise Technology staff will be conducting a combination of site surveys and remote assessment to validate coverage and performance.

A collaborative initiative

Supported by Enterprise Technology and campus teams

Wi-Fi Optimization is a collaborative initiative supported by multiple Enterprise Technology and campus teams, including:

Collaborating teams

  • University Operations: Planning, Design and Construction
  • Environmental Health and Safety
  • Campus technical support contacts and building managers

From the newsroom

In the news

Questions about your building?

Contact the networking team about the Wi-Fi Optimization project, or check your building in the tracker.